Orlando Indian Community - OrlandoIndian.com
| | | | | | | | | | | |
 


 

Question mark on fate of Jaitapur N-power plant as France orders technology audit

France,Technology

Author : Ranvir Nayar

International, National, France, Technology Read Latest News and Articles

Share With Your Friends



Add an Article

View All Contributions

Add To My Favorite

Add A Picture

Paris, July 7 (IANS) An independent audit has been ordered into the entire European Pressurised Reactor (EPR) project under implementation at Flamanville nuclear power plant, French Finance and Economy Minister Bruno Le Maire said. The plant has been under construction in north-western France since 2007.

Le Maire's orders came on Friday, barely a fortnight after the French Nuclear Safety Agency, ASN, ordered EDF, the constructor of the plant, to repair at least eight key welded joints that had not been done in accordance with safety regulations.

Proposed nearly two decades ago, the EPR was positioned as a state-of-the-art nuclear power technology and Areva, the then nuclear power company of France, began construction of the first project using EPRs in Flamanville in 2007.

More strikingly, even before its first reactor had been built and proven to be viable, Areva started aggressively marketing the technology to customers around the world, including Finland, Canada and of course India.

But the EPR has been a flop, at least so far. And Flamanville has become a national symbol of industrial shame and disaster for France, arguably the global leader in nuclear power technology, which accounts for over 70 per cent of French electricity production at extremely reasonable rates.

The Flamanville project has exceeded budgets repeatedly and has had innumerable safety audits after repeated incidents in the construction phase itself, leading Le Maire to order an overall review of the EPR itself.

"We need to understand what really has been going on in this project. We would like the EPR to be of the same standard as the best in the world," Le Maire said.

The audit puts a huge question mark first on the Flamanville project itself, especially as the latest deadline for the startup of the project given by EDF, which acquired an ailing Areva a few years ago, is barely two months away. This is almost certain to be pushed back again.

In 2007, when the 1650 MW project was launched, the construction was meant to be completed in five years with a total cost of Euro 3.3 billion. It has already taken 12 years and the cost has escalated to almost Euro 11 billion.

The latest delay and the audit will then have a serious impact on India-based Jaitapur nuclear power plant, which too has been delayed for over a decade despite a basic agreement between the Indian Nuclear Power Corporation (NPC) and EDF.

In 2008, India and France had decided to collaborate to build a 9.9 GW nuclear power plant, with six reactors of 1650 MW each. The project was touted as the largest industrial project ever to be undertaken in India and a major plank of Indo-French relations.

However, in the decade since the announcement, there has been little progress on the project and a lot has indeed changed in the global energy scenario, which raises existential questions about the feasibility and the need for such a large nuclear power project.

There is tremendous opposition to the project not just from environmentalists but also the residents of the site of the project, the village of Jaitapur, about 600 km south of Mumbai in Maharashtra. The villagers are worried about the large amount of land that would be acquired for construction of the six reactors and other facilities.

That aside, there are numerous other issues with Jaitapur. The first relates to the choice of the reactors, the EPR. It is indeed surprising that India opted for an entirely untried and untested technology. It does not help that practically even the few EPR projects that are under construction or planned have been bogged down by problems, including severe delays and extremely high cost overruns.

In 2015, the French nuclear safety agency said it had detected a very serious fault in the reactor vessel at Flamanville, causing another outrage against the project and indeed putting pressure on the French government to follow its European partners in reducing dependence on nuclear power.

The French government has since announced its aim of bringing nuclear power's share in the electricity mix down from the current 75 per cent to about 50 per cent.

The fate of other EPRs under construction is not very different from Flamanville. The construction of world's first EPR began in 2003 at Olkiluoto in Finland. Expected to be completed in 2009, the project has also suffered numerous delays and the latest pushback was announced in late November last year, putting the date of operationalisation to 2020.

Safety is another big reason behind Jaitapur residents' opposition to the project. France and India also have to walk the tightrope over the controversial issue of the ultimate responsibility related to safety.

While Indian law holds the equipment suppliers and constructors liable for any accidents that may occur, the French are hardly keen to engage in any venture with unlimited liability, especially when the plant would be operated by the Indian nuclear power producer, NPCIL.

The economic viability of the project is also questionable. Though the final cost of Jaitapur is yet to be ascertained, if Flamanville's one unit is expected to cost upwards of Euro 11 billion, the final cost of six reactors would be safely in the vicinity of Euro 70 billion.

Even in 2009, the cost of electricity produced at Jaitapur was pegged at around Rs 9 a kwh, nearly thrice the price of power from a coal-fired thermal power plant.

Moreover, the entire energy scenario in India has changed over the last decade, making Jaitapur look more like a white elephant than a much needed power source.

A decade ago, India was struggling with severe power shortages and the renewable energy was still in a nascent stage. However, in the last 10 years, the sharp mismatch in energy demand and supply has been bridged to a large extent and as a result many proposed power plants have stayed on the drawing board.

But the biggest change has come in from the renewable energy sector and that too mainly solar energy. In the last few years, solar energy generation in India has risen sharply and the government proposes to have an installed capacity of over 175GW of renewable energy by 2022, of which 100 GW would be solar.

In 2017, India added 4.6GW of solar energy capacity, taking the total to about 17GW. Solar energy production has been propelled ahead by extremely low prices for solar panels. As a result, power producers are selling electricity at below Rs 3 per kwh, with some bids actually coming closer to Rs 2.5 a unit.

In this situation, for any power producer or distribution company, it becomes impossible to justify prices that are triple or more, as is the case with Jaitapur.

Yes, solar energy is not available round the clock and wind energy depends on climatic conditions and India does need nuclear power to have an ideal energy mix with sustained power generation.

But the price has to be competitive and technology tried and tested. Currently, an Indian designed reactor costs about 2 million euros per MW, translating into Euro 3.3 billion for 1650 MW. Flamanville has already breached Euro 11 billion for the same capacity.

The two governments would have to look really hard for any reason to justify a project that would cost at least thrice as much, with an unproven technology.

(Ranvir Nayar is a senior Paris-based journalist. He can be contacted at r.nayar@mediaindia.eu)

--IANS

rtp


Copyright and Disclaimer: All news and images appearing in our news section, search engines and social media are provided by IANS. If you face any issues related to the content/images, please contact our news service provider directly. We are not liable/responsible for any content/images related to the news service provider.


Latest News

View More News


More News Articles

IPL 2024: All it needs is to win a couple of games and you are back in contention, says Rashid Khan

IPL 2024: All it needs is to win a couple of games and you are back in contention, says Rashid Khan

Aditi Rao Hydari's b'day wish for 'manicorn' Siddharth: 'Endless laughter, happiness'

Aditi Rao Hydari's b'day wish for 'manicorn' Siddharth: 'Endless laughter, happiness'

Why Vidya Malvade says she felt she would become 6 feet tall by end of 'Ruslaan' shoot